Cliffside Park Towne Centre

Towne Centre Photo Gallery

Redevelopment Updates:

March 13, 2017

Framing has begun in the north plaza lobby area.
The gazebo on the Anderson Ave. plaza area had the steel structure plumbed and leveled; ready for glass.
Stucco work is continuing around the exterior.
The roof on the south tower is completed and ready for finish pavers around the pool area.
Garage level #2 has had paint samples painted on a wall for decision of color.
The rear lot on Glen St. has been cleared, cleaned and leveled. The decorative retaining wall is ready to be finished.
The HVAC units are being started on the mezzanine levels.
Site work is continuing around the perimeter of the building.

March 24, 2017

Balcony panel work is mostly complete. Most all windows have been installed leaving just the penthouse and some corners to do.
Glass is being installed on the plaza level. Window walls are being erected along Lawton Ave.
The tops of the window walls on the plaza level are being framed and sheathed, closing in the lobby areas.
Block work has begun at the gazebo area on the plaza for the elevator. Curbing along the plaza leveled is being finished.
Finish stone work on the plaza stairs is continuing on Anderson and Lawton Aves. Decorative stone face samples have been installed on one set of stairs on Lawton Ave.
Stucco work is being cut in along finished stairs and garage ramp areas.
Light stations are being installed on Anderson and Lawton Aves. Trenches are dug for the electric lines.
Some framing has started in the south tower plaza level. All stairways from the building to the plaza level have been sheet rocked, taped and sanded.

Penthouse Floor:

Apartments and hallways have been taped and spackled. Stairways are taped and spackled to the top and sanded.
Access panels have been framed out in the hallway ceilings.
Apartment door bucks are installed and being painted.
Balcony corner glass panels are being installed.
HVAC units are installed.

12th floor:

Apartments and hallways are painted.
Hallway doors are installed.
Miscellaneous finish framing, rocking and taping is being done.

11th floor:

Apartments and hallways are taped and spackled ready for sanding.
Apartment door bucks are installed and painted.
Hallway doors are installed.
Framing and sheet rocking around windows being done.
10th floor:
Apartments and hallways are ready for sanding. Apartment door bucks are painted.
Floor is clean swept.
9th floor:
Apartments and hallways are ready for sanding. Apartment door bucks are painted.
Miscellaneous finish framing, rocking, taping and electric is being done.

8th floor:

Apartments and hallways are painted.
Cabinets are being installed.
Apartment doors are installed.
Miscellaneous finish work and electric are being done.
The floor is swept clean.

7th floor:

Apartments and hallways are painted.
Bathroom floor tile is being installed.
Apartment doors are installed.
Most all cabinets have been installed. The counter tops have been loaded.
Miscellaneous finish work being done.

6th floor:

Counter tops are distributed.
Bathroom wall tiles are being installed.
Apartment lights are installed.
Miscellaneous finish work being done.

5th floor:

Bathroom floor and wall tiles are installed.
Vanities have been distributed.
Cabinet tops are being installed.
Miscellaneous finish work is being done.

4th floor:

Floor is swept clean.
Counter tops are being protected with plastic sheeting.
3rd floor:
All bathroom walls and floors have been grouted. Vanities are being installed.
Window and elevator lobby areas have all been finished rocked and being taped.
Counter tops are protected.
The floor is swept clean.

2nd floor:

All electric in the apartments is wired and working.
Vanities are installed. Glass shower doors are installed.
Holes have been drilled for the kitchen cabinet handles.
Touch up finish spackling is being done.

1st floor:

Miscellaneous finish work is being done. The floor is clean swept.

Mezzanine floor #2:

The corner apartments are being framed. Miscellaneous finish work is being done.
The HVAC units are running heating the apartments.

Mezzanine Floor #1:

Miscellaneous Finish work is being done.
Work has begun in the retail area of the floor.

March 27, 2017

The weather has been up and down going from 70 degrees to 19 degrees within a week.
Plaza lobby walls and ceilings are being framed.
Exterior plaza ceilings are being framed.
Light stantions are continuing along Anderson and Lawton Avenues.
The penthouse windows are near completion. Corner balcony glass panels are being installed.
Electric is being run for the gazebo area. Block work is continuing here for the elevator.
Crushed stone has been put down on the lot on Glen St.
Sidewalk pavers are to be light brown squares with a reddish border.
Stucco finish work is being done throughout the site.
Finish stone work on the plaza stairs is continuing.
Framing is continuing in the plaza lobby area.
Glass panels are being installed on the south tower.

April 6, 2017

Most light stantions are installed and wired. Sidewalk pavers are scheduled to begin installation next week.
Verizon is hooking up their service to the building.
Wood floors are being installed on the mezzanine levels.
Toilets are being installed on the mezzanine levels.
Corner balconies at the penthouse are being installed.
Block work is being completed at the gazebo area. Concrete curbing and decking is being installed here.
Sidewalk pavers are to start on Glen St. this week.
Plaza exterior ceilings have been framed. The north tower lobby has been framed.
Only two corner apartment windows at the penthouse level are left to install.
Gas is ready to turn on tomorrow. Verizon’s service is hooked in.
Windows and exterior panels are being caulked. Glass is being installed on the south tower plaza level perimeter is being installed. The plaza and lobby areas are near complete.
The interior elevators are all ready to go.

Penthouse level:

Corner apartment windows are being installed. All other windows are finished.
The hallway fire doors have been installed.

12th floor:

Finish framing and rock work being done.

11th floor:

Apartments and hallways have been sanded, ready for paint.
Finish framing and rock work being done.

10th floor:

Apartments and hallways have been painted.
Framing and electric is being finished in the former hoist apartment.
Apartment doors have been distributed.

9th floor:

Apartments and hallways have been painted.
Kitchen cabinets are being installed. Apartment doors have been installed.
Miscellaneous framing and rocking is being done.

8th floor:

Bathroom floor tiles are being installed.
Kitchen cabinets are installed.

7th floor:

Bathroom wall tiles are being installed.
Framing and rocking around some window areas is being done. The elevator hallway area is being framed and rocked.

6th floor:

Miscellaneous finish work around windows is being done.
The hoist room has been sheet rocked.
The cabinet tops are installed.
Bathroom tiles are installed.
Apartment lights are trimmed and working.

5th floor:

Lights and smoke alarms are installed and working.
The kitchen sinks are installed.
The bathroom tiles have been grouted.
The hoist room apartment has been sheet rocked.

4th floor:

Miscellaneous finish work being done.

3rd floor:

Bathroom vanities have been installed.
Wood flooring has been distributed.
Kitchen sinks are distributed.
Miscellaneous finish work being done.

2nd floor:

Toilets are distributed. Wood flooring has been distributed.
The hoist room apartment has been rocked and taped. Finish work is being done.
Vanity tops are being installed.

1st floor:

The apartment entrance doors have been installed.
The toilets and sinks have been installed.
The hoist room is rocked and taped.
Some painting in the apartments is being done.

Mezzanine Level 2:

Permanent hallway lights have been installed.
Apartment entrance doors have been installed.
Wood flooring and base moldings have been installed in the apartments and a protective covering has been installed.
Apartment HVAC units are on and the apartments are heated.
Finish work is being done. Some finish paint samples have been painted in the hallway.
Sinks and tops are installed.

Mezzanine level 1:

Apartment doors have been installed.
Wood flooring and base molding has been installed in the apartments and protected.
Vanity tops and sinks are all installed.
HVAC units are on with most apartments heated.
The entire jobsite overall is clean.
There are approximately 120 tradesmen working on the site.