Cliffside Park Towne Centre

Towne Centre Photo Gallery

Redevelopment Updates:

January 13, 2017

Store front glass is being installed on the plaza level and balcony glass panels are distributed and being installed. A second glazier contractor has been hired on to help expedite closing in the buildings.
The concrete stairs on Anderson Ave. are moving forward with one set poured and the other being framed. Finished stone work around the fountain area on Anderson Ave. is being set.
Caulking is still proceeding around the building off of the hanging scaffolds.
Stucco is continuing in the rear Glen Ave side of the building.
The elevator at the north east corner of the site from the garages to the mezzanine is close to being finished.
Penthouse: Sheet rocking apartments is continuing.
12th floor: Sheet rocking is near completion.
11th floor: Sheet rocking is mostly done. Permanent lights in the mechanical rooms and garbage chute rooms are installed.
10th floor: Taping has begun. Balcony panels are being installed.
9th floor: Taping and spackling is being done. HVAC window units are being installed. Balcony panels are being installed.
8th floor: Second coat spackling is being done. HVAC window units are in and wood mantels are installed. Balcony panels are being caulked and sealed.
7th floor: Temporary heat is blowing on this floor. Balcony panels are being installed and caulked. The floor is swept clean preparing for the floor leveling pour.
6th floor: The floor is being poured with self- leveling cement. Floor protection is being put down. Door bucks are distributed and being installed.
5th floor: Apartment doors are being installed. Bathroom tiles are distributed. Spackled walls and ceilings are being finished sanding.
4th floor: Fire alarm pull boxes are installed. Fire alarm, cable and phone control boxes are installed in the mechanical rooms. All walls and ceilings are ready for paint. Painting has started. Bathroom tiles and balcony panels have been distributed.
3rd floor: The floor has been painted and bathroom floor tiles are being set.
2nd floor: Wooden apartment doors are being installed. Kitchen cabinets are distributed.
1st floor: Kitchen cabinets are being installed. Wood flooring been distributed.
M-2: Kitchen cabinets have been installed. Bathroom tile floors are being grouted.
M-1: Bathroom tile walls are being grouted.

January 19, 2017

Curbing completed along Anderson Ave. Front concrete steps from street level to the plaza have been poured. Miscellaneous form work around the front stairs and fountain area has been done.
Stairs on Lawton Ave. are getting the finish stonework installed. Storm drains on Lawton Ave. are being hooked in and ground is being leveled. Temporary electric panels here have been removed as permanent electric is installed.
The hoist tower is scheduled to be removed Friday the 20th. Exterior panels are to be installed as soon as the hoist tower is removed. The existing lot will then be cleaned up and graded.
The permanent water meter is ready to be installed. Electric is being installed now. Gas will be the last to hook in.
The interior elevator has passed state inspection and is ready to go.
The electric room on the plaza level for the south tower has been framed and rocked with electric panels installed. Stairwells on the plaza level for the south tower are being framed. Store fronts for this tower are being installed.
Stucco is continuing down the rear garage ramp.
Penthouse: Sheet rocking is continuing. The electric room meters are installed up to the top floor.
12th floor: Sheet rocking and taping going on.
11th floor: Taping with temporary heaters on.
10th floor: Floor has corner beads installed and is taped. Fire and smoke alarm lights are installed. HVAC apartment units have been distributed.
9th floor: HVAC units have been installed. Second coat spackle is done. Window panels on balconies are being installed.
8th floor: Stairway landings are poured up to this floor. Floor is prepared for the leveling pour. Wooden mantels over HVAC units are installed.
7th floor: The self- leveling floor has been poured. Finish taping is done.
6th floor: Door bucks are installed in the apartments. Stair way doors have been installed up to this floor. Hallway floors are protected.
5th floor: Bathroom tiles have been distributed. Fire pulls in the hallways have been installed.
Temporary heat is on here. Doors have been hung on the mechanical rooms.
4th floor: All rooms have been sanded and are being painted. Apartment wood doors are distributed.
3rd floor: Bathroom floor tiles are installed.
2nd floor: Kitchen and bathroom cabinets have been distributed. The floor is all painted. Apartment doors are hung. Bathroom wall tiles are being installed.
1st floor: Kitchen cabinets have been installed. Emergency lights in the apartments are installed.
Mezzanine 1 and 2: Kitchen cabinets and bathroom vanities have been installed. Bathroom tiles are installed and grouted. Glass shower doors have been installed.

February 1, 2017

The hoist tower and generator on Glen Ave. have been removed. Exterior panels are being installed. This should be completed by February 6th. At that time the lot on Glen Ave. will be cleaned and leveled.
Balcony window panels are being installed. Store front glass is being installed with deliveries every other day. Store front framing is near complete.
Steel gazebo to house the elevator from the garage levels to the plaza level on Anderson Ave. has been erected. This structure will be entirely enclosed with glass.
Storm drains on Anderson Ave. are being hooked up. Upon completion preparing for pavers along the roadway will begin. This is scheduled to take approximately 3 weeks to complete.
The block work for the fountain area is complete. Curbing has been done on Lawton Ave. The roadway on Anderson Ave. and Lawton Ave. is being leveled off to allow parking there again.
Building caulking is nearly complete. Stucco is moving down the garage entrance ramp.
Sheet rock has been delivered for the plaza level area.
One interior elevator is running with the other two to start soon. Floors and walls are being blocked in around the last two elevator entrances on all floors.
Penthouse: Sheet rocking is near complete. Mechanical room doors have been installed up to the top with locks installed.
12th floor: Taping and spackle being done.
11th floor: Taping and spackle being done.
10th floor: Floors are being prepared for leveling compound to be poured. Some spackling is being finished.
9th floor: The floor has been poured. Walls and ceilings are ready for sanding.
8th floor: Apartment door bucks have been installed.
7th Floor: Hallway floors have been protected. HVAC wall units are installed.
6th floor: Balcony glass panels are being installed and caulked.
5th floor: Tiles for the bathrooms have been distributed.
4th floor: Kitchen cabinets are being installed. Painting is near complete. Bathroom floor tiles are being installed. Apartment wooden doors have been distributed.
3rd floor: Kitchen cabinets and vanities are nearly complete. Counter tops are loaded on the floor. Apartment doors are hung. Bathroom floor tiles are done, wall tiles are being installed.
2nd floor: Kitchen cabinets and counter tops are all installed. Vanities are in. Apartment doors are all hung. Bathroom wall tiles are being installed.
Mezzanine levels: Kitchen cabinets and tops are all installed. Ceiling lights in the kitchens are working. Bathroom tile work is complete. Vanities are installed. Glass shower doors are installed. Apartment fire alarms are installed.

South tower:
The pool has been installed on the roof. Elevator work has begun. Steel stairs have been poured and are being framed out. Drains on the plaza level are all hooked in. Electric and fire alarm wiring is being installed in the stair ways.