Cliffside Park Towne Centre

Towne Centre Photo Gallery

Redevelopment Updates:

June 27, 2017

The gazebo glass wall panels are being installed.

The fountain on Anderson Ave.’s plumbing and drains has been completed.

Windows are being installed at the southeast ground floor office area. Glass panel caps and trim work is being installed at the southeast tower. South tower roof top deck tiles are still being installed. The roof top walkway tiles are being installed. Roof perimeter railings are continuing.

Plaza ceilings are being finished. Plaza stone stairs are finished. Decorative stone face is continuing down the north access driveway. Plaza perimeter stone caps are being installed.
Lobby area is being finished sheet rock and spackle. Lobby canopy plywood has been installed.

Garage entrance apron on Lawton Ave. is framed and ready to be poured. Garage levels 1&2 are finished painted. Garage level 3 has been spray insulated and fire safed. All garage lighting and exit signs are installed. Security and fire alarm boxes for building access doors are installed.

Penthouse level: Finish coat of paint is being done. Vanity tops, byfold doors and entrance door saddles are installed.

12th Floor: Touch up spackle being done.

11th Floor: Clean swept. Kitchen back splash wall tiles are being installed. Entrance door handles are installed.

10th Floor: Hallway and apartment lights are installed.

9th Floor: Kitchen faucets are installed. Wood flooring has been started. Toilets are loaded. Some touch up work being done. Floor is clean swept.

8th Floor: Wood flooring being installed. Base molding is being installed. Toilets have been distributed.

7th Floor: Base moldings are completed. Toilets are being installed.

6th Floor: Appliances are being distributed. Carpeting in bedrooms is being installed. HVAC units are being hooked up. Thermostats and outlet covers are in.

5th Floor: HVAC’s are running. Bath room wall lights are installed.

4th Floor: Microwaves are installed. Bathroom faucets are installed. Apartment door knobs and cabinet handles are installed. Apartment illuminated numbers are installed in hallways.

3rd Floor: Appliances have been installed.

2nd Floor: Apartments are mostly finished. Floor is cleaned.

1st Floor: Shower heads and bathroom fixtures have been installed.

Mezzanine level apartments are mostly complete. Commercial areas are being worked on.

July 11, 2017

The last areas of the plaza deck around the gazebo area have been poured. The deck has been sealed and is ready for finished decking. Gazebo roof glass panels are being installed.
The rear parking garage level ramp has had the finish surface completed. The apron for the entrance to the rear garage level ramp has been finished. Sidewalk pavers from the top of Lawton Ave. to the north access driveway on Anderson Ave. are completed.

The fountain on Anderson Ave. has the wire mesh in and is ready to pour concrete.

The lobby canopy is framed and roof finished. The lobby is being taped.

The perimeter of the site has been cleaned and new safety netting has been erected.

Stone work on the perimeter of the plaza and stairs is mostly complete.

Penthouse: All kitchen and bathroom cabinets and tops are installed. Bathroom tile work is completed. Kitchen wall tiles are being installed. All apartment doors are installed. Entrance door hardware is installed. Wood mantles over HVAC units are complete. Toilets are distributed. Wood flooring is being loaded. Hallway ceilings are being replaced due to a water leak.

12th Floor: Lighting in the apartments is complete. All cabinets, tops and doors are installed.

11th Floor: Wood flooring is loaded. Some touch up work being done.

10th Floor: Floor is clean swept.

9th Floor: Wood flooring is being installed. Kitchen faucets are installed. Apartment door and cabinet handles are installed. Base moldings are being installed. Hallway lighting is installed.

8th Floor: Bedroom carpeting is being installed. Toilets and shower doors are being installed. Bathroom fixtures are in. All outlets, switches and cable connection covers are on. Byfold doors are in. have been distributed. HVAC units are running.

7th Floor: Apartment illuminated hallway numbers are installed. Appliances are being installed.

6th Floor: All appliances are installed. Exterior balcony lights are installed.

5th Floor: Appliances are installed. Apartments are complete.

4th Floor: Apartments are complete.

3rd Floor: Apartments are complete. The hallway is ready for the finished paint.

2nd Floor: Apartments are complete. Hallways are ready for paint.

1st Floor: Apartments complete. Gym and shower area floors are being laid and the walls have been painted. The pool access area is near complete.

Mezzanine Floors: The hallways have been finished painted. Hallway floors have been flash patched for finish carpeting.

July 18, 2017

The floor inside the gazebo is ready to pour concrete. Gazebo glass wall panels are complete. Glass doors are being installed. Roof panels have been installed with a protective covering on.

The elevator inside the gazebo is complete. The shaft walls are having decorative stone work applied.

The southeast corner ground floor office windows are being completed. The southeast stairway is being framed. The roof over the offices is being completed. The south tower is empty and is being swept clean. Roof tiles continue to be installed on the south tower.

The plaza ceilings are complete. All ceiling lights have been installed. Plaza tile decking has begun installation. Building access doors from the plaza have been installed with all locks and handles.

The entrance lobby is having finished wood panels installed. All beams and columns are being wrapped with finished wood panels. Rear offices are finished and being painted.

Exterior balcony lights are complete. Bolts are being set for side walk lamp posts. All side walks have been swept clean.

Penthouse: New roof drain pipes are being installed in the hallways. Most all kitchen and bathroom cabinets and tops are installed. Toilets are distributed. Some apartment painting and touch up work is being done.

12th Floor: Cabinets and tops are complete. Toilets are distributed. Some touch up and painting is being done.

11th Floor: The floor is swept clean. Toilets are being installed.

10th Floor: Wood flooring is being installed.

9th Floor: Some touch up work is being done. Wood floors are complete. Carpeting is being installed. Appliances are being distributed and installed.

8th Floor: The hallway has been painted the finish coat. Appliances are being installed.

7th Floor: Some touch up work is being done in the hallway. Apartments are mostly complete. Appliances are installed. HVAC units are running.

6th Floor: Apartments are mostly complete. Some touch up work being done. Refrigerators are being installed. HVAC units are running. Hallway is painted.

5th Floor: Apartments are complete. Hallway is painted.

4th Floor: Apartments are finished. Hallway is ready for paint.

3rd Floor: Apartments are done. Hallways are painted.

2nd Floor: Apartments are done. Hallway is painted.

1st Floor: Apartments are done. Hallways are painted. Gymnasium floors are installed and walls have been painted. Shower room floors have been sealed a walls are ready for finish work. Access doors to the south roof top pool area are all in with handles and locks.

Mezzanine Floors: Apartments are complete. Hallway is painted. Commercial areas are being painted. Areas are all swept clean.